How the work gets done

Dawndrums works across the stack: hardware design, Linux systems engineering, software, testing and integration, and documentation. This page describes the disciplines and links to the real artefacts.

Disciplines

Hardware development

Requirements, architecture, schematics, board layout, PCBA production runs and board revisions informed by bring-up.

Linux systems engineering

Bootloader, kernel, device tree, drivers and firmware integration, with preference for mainline interfaces.

Software

DawnOS system integration and applications such as divine-camera, built on libcamera and KDE Plasma Camera.

Testing

Subsystem bring-up tests, system integration and test phases, and validation before each board revision.

Integration

Making hardware, kernel and user space behave as one product: power, thermals, media, connectivity.

Documentation

Technical documentation for developers, published as it matures.
docs.dawndrums.tn

Engineering log

Completed engineering stages

Stages recorded as completed in the Divine D. engineering log. Dates are the planning windows recorded at the time. Current and future work is published on the Divine D. roadmap.

Hardware

10 stages
  1. State of the art, concept and planning
    1 May 2023 – 30 August 2023
  2. Architecture
    1 September 2023 – 30 September 2023
  3. Preliminary prototyping
    1 October 2023 – 15 November 2023
  4. Final requirements and KPIs
    16 November 2023
  5. Schematics and layout
    16 November 2023 – 31 January 2024
  6. PCBA manufacturing — Hannibal batch (rev. 1.0)
    15 February 2024 – 1 May 2024
  7. First PCB
    1 May 2024
  8. Board bring-up, phase I
    1 May 2024 – 2 March 2025
  9. Lessons learned (rev. 1.0)
    2 March 2025
  10. Main board revision 1.1
    March 2026

Software

5 stages
  1. DawnOS: bootloader and kernel, phase I
    15 February 2024 – 30 April 2024
  2. System integration and test, phase I
    1 May 2024 – 30 May 2024
  3. Software test results, phase I
    30 May 2024
  4. DawnOS: drivers and firmware, phase II
    1 June 2024 – 30 August 2024
  5. System integration and test, phase II
    1 September 2024 – 30 December 2024

Community and resources

Repositories, documentation and discussion

Technical discussion happens in public. Join the forum or chat, read the documentation, or follow the code.

Only material Dawndrums is entitled to publish is released. Confidential, incomplete or third-party proprietary material (for example vendor firmware or datasheets under NDA) is not presented as open source.